Kotkamills to start the new board machine in July

19 May 2016

Kotkamills' construction work of the new board machine 2 (BM 2) has progressed to the very advanced stage. The start-up of the new board machine will take place during July 2016, as the company says in the press release received by Lesprom Network.

As an outcome of the Flying Eagle project a printing paper machine is converted to board machine producing recyclable, repulpable and renewable consumer board products.

After shutdown and fast demolition of PM 2, the construction work of the new BM 2 started in February at Kotkamills in Kotka, Finland. The intensive project has demanded extensive work from both Kotkamills personnel as well as from external suppliers.

Kotkamills is a forest products company based inFinland. The company specialises in laminating paper, matt coated bulky paper and sawn products.

 

Source : lesprom.com